Home /UOS — University of Sargodha /IT Project Management

IT Project Management BS Information Management/BS Management 4 Semester/Term University Of Sargodha (UOS) 2023

IT Project Management BS Information Management/BS Management 4 Semester/Term University Of Sargodha (UOS) 2023 — page 1

Discussion

Ask a question about this paper, or help someone else with theirs. Answers are emailed to whoever asked.

Your email is only used to send you replies and occasional Ustadni updates. It is never shown publicly.

Log in to post under your name

No questions yet — be the first to ask.

More IT Project Management papers

See all

Paper text

=

University of Sargodha

/

BS 4' Term Examination 2023

Subject: Information Technology

Paper: IT Project Management (ITCC-202)

Time Allowed: 02:30 Hours

Maximum Marks: 60

Note:

Objective part is compulsory. Attempt any three questions from subjective part.

Objective Part

(Compulsory)

Q.1.

Write short answers of the following in 2-3 lines each on your answer sheet.

Explain WBS.

i1.

iii.

iv.

V.

vi.

vii.

vili.

ix.

x.

xi.

xii.

Explain Scope creep.

ani. o

Explain Project charter.

Explain Positive Risks.

Explain project mitigation.

Define an activity.

Explain PMI knowledge areas.

Explain difference between AOA and AON.

What is meant by Risk reduction?

What is a Gantt chart?

What is Brainstorming?

Define the approaches of agile methods.

(2*12)

ustadni.com

Subjective Part

(3*12)

Q.2.

Q.3.

Q.4.

Q.5.

Q.6.

ustadni.com

Explain RELATIONSHIP OF PROJECT, PROGRAM, PORTFOLIO.

a) Explain different type of contracts.

b) Explain different types of organization structures and draw diagrams.

What is Configuration management? Differentiate between version control and Configuration

control.

Explain function point estimation,cocomo estimation and Line of code software estimation

techniques with examples.

Consider the following scenario and answer the following question

Activities

Predecessor

Duration

A

10

B

15

5

B

C,D

12

14

8

G

D,F

E

E,G

15

10

J

a) Draw the project network diagram.

b) Develop the project schedule (EST, EFT, LST, LFT)

c) What are the critical activities and critical path?

d) What is project completion duration?

ustadni.com