Home /University Of Sargodha (UOS) /IT Project Management

IT Project Management BS/MPhil Information Technology/MS Information Technology 4 Semester/Term University Of Sargodha (UOS) 2021

IT Project Management BS/MPhil Information Technology/MS Information Technology 4 Semester/Term University Of Sargodha (UOS) 2021 — page 1

Discussion

Ask a question about this paper, or help someone else with theirs. Answers are emailed to whoever asked.

Your email is only used to send you replies and occasional Ustadni updates. It is never shown publicly.

Log in to post under your name

No questions yet — be the first to ask.

More IT Project Management papers

See all

Paper text

Subject: Information Technology

Time Allowed: 02:30 Hours

University of SargodhaßS 11-29394

BS 4"' Semester/ Term Exam 2021

Paper: I.T Project Management (ITCC-202)

Maximum Marks: 80

Note: Objective part is compulsory. Attempt any three questions from subjective part.

Objective Part

(Compulsory)

Q.1.

Write short answers of the following in 2-3 lines each on your answer sheet.

i.

її.

Explain Negative risk.

Explain types of stakeholders.

iii.

Explain Project charter.

iv.

Explain forecasting with respect to project management.

V.

Explain Agile process model.

Vi.

Define Risk control.

vii.

Explain process monitoring and controlling.

vili.

Explain Change Management.

ix.

Explain change control.

Explain Gantt Chart.

Explain risk mitigation.

xii.

xiii.

xiv.

Explain outsourcing.

Explain Milestone.

Explain Cash flow.

xvi.

Explain types of contracts in procurement.

Explain LOC.

(2*16)

ustadni.con

Subjective Part

(3*16)

Q.2.

Draw a network diagram and calculate critical path

activities

predecessor

Duration (days

START

A

A.B

(16)

20

10

30

10

20

G

EX

Q.3.

What are various techniques project scope management? Explain in detail work BREAK DOWN

STRUCTURE Draw Diagram of WBS.

(16)

Q.4. Explain Resource scheduling techniques and identify resource requirements in any software project.

(16)

Q.5.

a) Explain Cost benefit analysis techniques.

(16)

b) How can you evaluate and review performance of any software project.

Q.6.

Explain PERT how can we apply PERT on any software project give example. Why do we use

PERT in any software project?