IT Project Management/Management/Project Management AD/MS Project Management 4 Semester/Term University Of Sargodha (UOS) 2025
Discussion
Ask a question about this paper, or help someone else with theirs. Answers are emailed to whoever asked.
No questions yet — be the first to ask.
More IT Project Management papers
See all
IT Project Management BS/MPhil Information Technology/MS Information Technology 4 Semester/Term University Of Sargodha (UOS) 2024
Uploaded 1 year ago
Download ↓
IT Project Management BS Information Management/BS Management 4 Semester/Term University Of Sargodha (UOS) 2023
Uploaded 1 year ago
Download ↓
IT Project Management BS/MPhil Information Technology/MS Information Technology 4 Semester/Term University Of Sargodha (UOS) 2021
Uploaded 1 year ago
Download ↓
IT Project Management Msc IT 4 Semester/Term University Of Sargodha (UOS) 2023
Uploaded 3 years ago
Download ↓
IT Project Management BS/MPhil Information Technology/MS Information Technology 4 Semester/Term University Of Sargodha (UOS) 2021
Uploaded 3 years ago
Download ↓
IT Project Management BS IT 2015 UOS
Uploaded 3 years ago
Download ↓
Paper text
University of Sargodha
Subject: I.T Paper: IT Project Management (IT-4349)
\ Time Allowed: 02:30 Hours \ PEAR YR 51
Note: Objective part is compulsory. Attempt any three questions from subjective part,
Objective Part. (Compulsory)
Q.1. Write short answers of the following in 2-3 lines each on your answer sheet. (2*12)
i. In the context of “Albrecht function point analysis”, give an example of “External inquiry”.
ii. What is the difference between objectives and goals of a project?
iii. What is a Work Breakdown Structure (WBS)?
iv. In the context of Network Models (that represent activities and their relationships), what is meant
by Hammock activities?
v. Provide a few advantages of project portfolio management.
vi. Provide two disadvantages of the “Incremental Delivery” approach of software development.
vii. Why may some managements favour the waterfall approach?
vill BR er Ee rs Jars ar TEL A vt ant rmat nm tH tA TD
M.Sc. 4!" Semester Examination 2025
Paper: IT Project Management (I1T-4349
Maximum Marks: 60
Subject: I.T
* Time Allowed: 02:30 Hours
In the context of Network Models (that represent activities and their relationships), what is meant
viii. Discuss the analogy-based effort estimation technique.
ix. When preparing a Work Breakdown Structure (WBS), what problems arise if a WBS has too great
or too shallow depth?
What is the purpose of the critical path method in the context of network planning models?
xi. Write down the steps performed during Red/Amber/Green (RAG) reporting.
xii. What is meant by earned value analysis?
ig Tey
)
Subjective Part (3*12)
Q.2. In the context of software development methods, discuss the Dynamic Systems Development
Method in detail.
Q.3. Discuss the following cost-benefit evaluation techniques:
e Return on Investment
e Net Present Value
Q.4. Discuss the COCOMO model. How does it perform effort estimation?
Discuss Program Evaluation and Review Technique (PERT) in detail with the help of an example.
Q.6. Discuss the Gantt chart and the Slip chart with the help of an example of each.